Unnao News: Questions on standards were raised at the time of formation, the same road was uprooted in six months

Satish Kumar
3 Min Read

Unnao News. The sports were opposed by the villagers in the standards being made during the construction of the road. But the villagers were ignored. Now the same road has started to be uprooted in just six months. Due to which the vehicle riders are facing difficulties and accidents in traffic.

The Maula road connected to the Hasanganj-Munshiganj road was repaired for one km at a cost of eight lakhs six months ago. The villagers protested seeing the quality -less construction at the time of the road, but the hearing was not held. On which the road started to be uprooted only after two months of construction.
Now it has been six months and the ballast of the entire road has become gravel. On which bikes and bicycle riders have started slipping and falling.

Dozens of villagers, including village heads Shashikant Singh, Ajay Shukla, Guddu Mian, Abdul Salam, Sanu, Atul, Rajatol Singh, alleged that when the road was being built, the quality was done only when the quality was constructed, which was also complained, but did not improve.

In 6 months, the road has completely turned into ballast. Due to which bicycles and bikes slip and fall and get injured. The villagers are collecting the road in front of their homes and collecting the road.
The villagers have investigated and demanded action. JE Praveen Katiyar said that the contractor who was contract for the road was contract. The contractor died before the construction started, after which the construction was done by the contractor’s wife. Another contractor has been asked to correct the road again. Soon the road will be corrected.
Corruption was opened in the construction of Mohan Auras Marg

The road started to be uprooted within a month due to the construction of Mohan-Auras route. On which the villagers gathered ballast on the road and put the shore. The villagers had alleged a qualityless construction alleging corruption in construction. After the case was exposed, the authorities had re -tasked the 1.5 km route to the same contractor.