Story Behind Hebbal Downramp: BDA engineers camped onsite, slept on factory floors & skipped family events to push the project
Story Behind Hebbal Downramp

BENGALURU: This is the story of sweat, toil, and dedication of Bangalore Development Authority (BDA) engineers to outsmart the clock and see the Hebbal flyover downramp project through in record time because of false starts. Sleeping on factory floors and snatching just 2-3 hours of sleep, having meals at roadside dhabas, letting go of family time, festivals and New Year celebrations are some of the sacrifices made by engineers to recoup the time lost to bureaucratic wrangling.The long-awaited downramp is finally ready, much to the relief of commuters in north Bengaluru — after nearly 10 years of planning and repeated delays. BDA completed the 6-metre-wide and 1km-long ramp in Jan in under 18 months after overcoming multiple administrative, technical, and logistical challenges.

10 years of delay, 1.5 years of non-stop work: The story behind Bengaluru’s Hebbal downramp

The ramp proposal was stuck for years because of design changes, land-use constraints, and prolonged bureaucratic approvals. When work resumed in early 2024, engineers had to coordinate continuously with Metro and railway authorities, urban transport agencies, and vendors to keep the project moving. Night-time construction, customised design adjustments, and real-time problem-solving ensured steady progress despite complex conditions such as active traffic, railway operations, and overlapping Metro and transport projects.

Bengaluru: CJ Roy Death, SI Bribe Arrest, 4 Assam Workers Found Dead and More

The project demanded no less than 100 on-site visits — at last count — by the BDA team.Assistant executive engineer Sharan MS, who along with a seven-member team worked tirelessly, said: “I had been married for just one month when I was sent to Ludhiana last year to oversee the manufacture of bolts to ensure they met the required standards. I don’t know about commuters, but my wife is extremely happy that the Hebbal ramp work is finally done.”

10 years of delay, 1.5 years of non-stop work: The story behind Bengaluru’s Hebbal downramp

Umesh BR, executive engineer, said his son is “now very happy” because he gets to spend time with dad. “We hardly spent time with family. Our two years of hard work has paid off.”Explaining how the team completed work in just 1.5 years, Suresh R, executive engineer, said: “We visited the site and multiple offices every week. That is why we could do what would have otherwise taken three years. Normally, a project like this takes three years after approval. We completed it in less than half the time because we stopped working in silos and took ownership.”Umesh added: “For two years, we worked without breaks. There were no festivals, no New Year celebrations. We were either on site at night or running between offices during the day.”



Source link

Share This Article
Follow:
Saroj Kumar is a digital journalist and news Editor, of Aman Shanti News. He covers breaking news, Indian and global affairs, and trending stories with a focus on accuracy and credibility.
Leave a Comment

Leave a Reply

Your email address will not be published. Required fields are marked *